Title 18 SUBDIVISIONS
Chapter 18.28 BUILDING PERMITS
18.28.010 Subdivisions generally.
18.28.020 Subdivisions with minor improvements.
18.28.030 Subdivisions with major improvements.
18.28.040 Occupancy.
18.28.050 Consolidation map.
18.28.010 Subdivisions generally.
Building permits for the erection of buildings in a subdivision will be
issued upon the final approval of improvements required by section 18.20.270.
(Ord. 789 § 1 (part), 1974: prior code § 11-1.18(a))
18.28.020 Subdivisions with minor improvements.
Building permits for the erection of buildings in a subdivision where only
minor improvements are required may be issued prior to final approval of
improvements required by section 18.20.270, where the director is satisfied all
of the following conditions are met:
A. The lot is serviced by a street
adequate to provide access thereto;
B. The lot may be adequately served
by the existing water system and existing sewer or other sanitary
system;
C. Service laterals for water, sewer and electricity as well as
sidewalks, curbs and gutter and other minor improvements as required will be
completed within three months from the issuance of a building permit, or within
a longer period where the subdivider shows by a construction schedule or
otherwise that more than three months is required for the erection of the
building; and
D. The construction of subdivision improvements is bonded
pursuant to sections 18.20.180 through 18.20.220. (Ord. 789 § 1 (part),
1974: prior code § 11-1.18(b))
18.28.030 Subdivisions with major improvements.
Building permits for the erection of buildings in a subdivision where
major improvements are required may be issued prior to the final approval of
improvements required by section 18.20.270, in the following
situations:
A. For a building to be used as a model home;
B. For
buildings to be constructed by or on behalf of the subdivider and intended to be
sold, leased, or rented together with the lot;
C. Where the director is
satisfied by the construction schedule of the subdivider, or otherwise, that the
building will not be completed before improvements to the subdivision are
completed and all subdivision improvements are bonded pursuant to sections
18.20.180 through 18.20.220. (Ord. 789 § 1 (part), 1974: prior code §
11-1.18(c))
18.28.040 Occupancy.
Occupancy of any building in a subdivision will not be allowed until and
after final approval of improvements required by section 18.20.270 is given;
provided, however, that where the director, the director of public works, the
director of water supply, the sanitary engineer and other involved officials are
satisfied that there will be no detriment to the public health, safety or
general welfare, and an occupancy permit has been issued, buildings may be
occupied prior to final approval of improvements required by section 18.20.270.
(Ord. 789 § 1 (part), 1974: prior code § 11-1.18(d))
18.28.050 Consolidation map.
A. When a building or a group of buildings forming a singular development
is contemplated in two or more contiguous lots in a manner that the common
boundary line is disregarded, or when any one of the lots is substandard in size
or width, then a consolidation map shall be filed prior to the issuance of a
building permit. Improvements shall not be required for the approval of the
consolidation; provided, however, should the consolidation be followed by a
resubdivision establishing more lots than in existence prior to the
consolidation, then improvements according to this title shall be
required.
B. The director may approve the building permit should the
preliminary consolidation plat conform basically to the requirements of the
final plat; revisions to the consolidation plat for strict conformance of the
final plat shall be made by the subdivider and filed with and approved by the
director prior to the occupancy of the building. (Ord. 789 § 1 (part),
1974: prior code § 11-1.19)